| Item |
Completion Date |
Notes |
| A. Security Monitor |
Finished |
|
| B. Aluminum Railings |
Finished
|
|
| C. Wallpapering |
Finished
|
Papering of intercom and mailbox walls to be completed upon installation of those items. |
D. Painting of Elevator
Door and Frame |
Finished
|
|
| E. Tile Work |
Finished
|
|
| F. Intercom |
Finished
|
Memo sent to tenants requesting feedback on any problems. |
| G. Door Signage |
Finished
|
|
| H. Vestibule Walk Off Mat |
Finished
|
|
| I. Mailboxs |
04.25.08
|
Intalling 04.21.08. Memo sent to tenants on 04.18.08 |
J. Heating Vent Grill
Below East Mailboxes |
05.02.08
|
Backordered 03.27.08, requires 6 weeks lead time |
| K. Rubber Stair Treads |
TBD
|
Original material rejected. New treads ordered |
| L. Aluminum Wall Plate and Metal Trim for Mirror |
Finished
|
|
| M. Doors |
TBD
|
Interior doors to be totally replaced. Exterior door missing astragal and brushes. |
Projected Date of
Substantial Completion |
04.28.04
|
|